Rapid work to build our foundation - October 6 & 7

updated October 15


Wednesday, October 6, 2004 10:00 am

The lot has been cleared and stakes sets to indicate the corners of the foundation.
Wednesday, October 6, 2004 3:00 pm

By that afternoon, the forms have been set for the foundation.
Thursday, October 7, 2004 10:30 am

By the next morning, the foundation fill has been put into place.
At the far end, this dirt is four feet deep.
Monday, October 11, 2004 3:00 pm

Plumbing begins to be set in the foundation. This is all PVC pipe which is used for drains and vents.
Friday, October 15, 2004 10:00 am

Major trenches have been dug. These will become the major beams within the slab when the concrete is poured. Plastic now covers the dirt.




2004 Chris Guinn
updated 10/15/2004